Answers can be found in PMBOK
8 October 2011
3 October 2011
A process is likely to be not out of control when
Note: Answer can be found by referring PMBOK
Labels:
Control Chart,
PMBOK,
PMP,
Practice Question,
Tricky Question
Change requests are an output of all the following processes except
Labels:
Change Requests,
Easy,
PMBOK,
PMP,
Practice Question
Control Charts
Control Charts: are used for determining stability of a process. Important
terms are:
USL - Upper Specification Limit
LSL - Lower Specification Limit
UCL - Upper Control Limit
LCL - Lower Control Limit
First two are set by customer and last two are normally (+-) 3 Sigma.
Normally used to track repititive activities, sometimes they are also used
to monitor
cost and schedule variances, volume and frequency of scope changes.
A process is out of control when seven consecutive data points are above or
below the mean.
terms are:
USL - Upper Specification Limit
LSL - Lower Specification Limit
UCL - Upper Control Limit
LCL - Lower Control Limit
First two are set by customer and last two are normally (+-) 3 Sigma.
Normally used to track repititive activities, sometimes they are also used
to monitor
cost and schedule variances, volume and frequency of scope changes.
A process is out of control when seven consecutive data points are above or
below the mean.
20 September 2011
- Critical Path V Critical Chain
This post is available at http://letslearn.ritsin.com/
Labels:
Critical Chain,
Critical Path
19 September 2011
-Ishikawa – Cause and Effect diagrams
This post is available at http://letslearn.ritsin.com/
15 September 2011
- 4.1 Develop Project Charter
This post is available at http://letslearn.ritsin.com/
Labels:
Initiating,
Integration Management